ENEC Announces Completion of Initial Construction Work for Unit 1 of Barakah Nuclear Energy Plant & Progress Update Towards Safety-led Operations

05.05.17

- ENEC completes handover of Unit 1 systems to KHNP for commissioning, marking end of initial construction activities for the first of four units of the Barakah Project

- KHNP will lead the commissioning work of the first UAE-based APR-1400, as part of the scope of the 2009 Prime Contract 

- Federal regulatory approval from FANR, in addition to international nuclear assessments from IAEA and WANO, will be required before fuel assemblies can be loaded into Unit 1

Emirates Nuclear Energy Corporation (ENEC) has announced that it has, together with Korea Electric Power Corporation (KEPCO), completed initial construction activities for Unit 1 of the Barakah Nuclear Energy Plant and the turnover of all plant systems to Korea Hydro and Nuclear Power (KHNP) (a subsidiary of KEPCO) for testing and commissioning, in preparation for safety-led nuclear operations.

The completion of initial construction work of Unit 1 was preceded by the successful completion of the Hot Functional Test (HFT) at the end of 2016.  The HFT is one of the major testing requirements under the Construction License for Units 1 & 2, which was granted by the Federal Authority for Nuclear Regulation (FANR) in 2012.

ENEC signed the Prime Contract with KEPCO in 2009 for the construction of the Barakah Plant. The handover of Unit 1’s 277 systems from KEPCO to KHNP for commissioning marks the end of initial construction activities of Unit 1 and the start of the preparatory phase for nuclear operations.

“The completion of Unit 1 construction activities and the handover of all systems for commissioning are important milestones in a project that is critical to the future energy mix of the UAE, and they reflect the professionalism and dedication of everyone involved in the project,” said Mohamed Al Hammadi, Chief Executive Officer of ENEC.

Following the satisfactory completion of commissioning activities by KHNP, Nawah Energy Company (Nawah), a joint venture between ENEC and KEPCO established to operate Barakah Nuclear Energy Plant Units 1-4, will assume operational responsibilities for Unit 1.

However, as per UAE regulatory law, the construction, start-up and operations of nuclear energy plants are subject to regulations issued by the Federal Authority for Nuclear Regulation (FANR), and the loading of fuel and actual operation of Unit 1 will require the approval of FANR and the issuance of an operating license. FANR is conducting a rigorous and stringent review of the operating license application, which was submitted by ENEC in March 2015, and carrying out numerous inspections of construction and  operational readiness to support this review. 

In addition to the extensive review by FANR, senior nuclear experts from the International Atomic Energy Agency (IAEA) and the World Association of Nuclear Operators (WANO) will also conduct a series of voluntary, but independent assessments of the robustness of the operating infrastructure and the proficiency of the operations personnel that will ultimately bring Unit 1 into full commercial operation.

“As part of the commitments made to the international nuclear community in its 2009 white paper, the UAE pledged that its nuclear operations would be guided by IAEA and WANO standards and best practices, and we look forward to continuing our work with these entities and to benefitting from their insights and experience as we realise this commitment,” said Al Hammadi.

Only after the successful conclusion of these legally-mandated and voluntary reviews, and upon FANR approval of the Operating License for Unit 1, will Nawah proceed with Unit 1 fuel load and plant start-up.

“Nawah is currently working with the IAEA and WANO on the approach and timetable for their operational readiness assessments at Barakah later this year. These assessments will take place before we anticipate being granted our Operating License by FANR and begin the process of loading fuel assemblies into the reactor. The entire Nawah team is fully aligned around the objective of safe, reliable, and efficient operation of the first nuclear energy plant in the UAE,” said Mohammed Sahoo AlSuwaidi, Acting CEO of Nawah.

“As we move toward Unit 1 Fuel Load, we recognize the scale of both our responsibilities and of the challenges that lie ahead of us. Nawah’s commitment to meeting the highest standards of safety and quality in nuclear operations is what drives the work of all our personnel, who are striving to ensure that we meet FANR’s expectations and obtain regulatory approval to begin the start-up of Unit 1,” said AlSuwaidi.

“Following the receipt of all necessary approvals and the initiation of plant start-up, Unit 1 power levels will be increased in stages and the first megawatts of electricity from peaceful nuclear energy will be delivered to the UAE grid. Testing, of both safety and operating systems, will be conducted at each stage of this process over a period of several months,” Al Suwaidi explained.

ENEC also announced the approval by its Board of Directors of a timeline update for the start-up of Unit 1, driven by a desire to achieve the highest possible nuclear quality and safety standards. The approval follows a series of assessments by ENEC, Nawah and international experts, as well as lessons learned from Shin Kori Unit 3 in South Korea, the reference plant for Barakah. The timeline includes an extension for the start-up of nuclear operations for Unit 1, from 2017 to 2018, to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as a reinforcement of operational proficiency for plant personnel.

“Since 2009, ENEC has pursued the highest standards of nuclear quality, safety and operational transparency,” said Al Hammadi.

“The approval of a timeline update projecting the initiation of Unit 1 nuclear operations in 2018 reflects the conservatism of  ENEC’s management and Board of Directors, as well as our local, federal and international stakeholders, all of whom stand firmly united in the belief that long-term sustainable operations begin with strict adherence to nuclear safety. We believe that our continuous focus on quality and safety will position the UAE as a trusted contributor to the community of nuclear operators around the world,” continued Al Hammadi.

The Barakah Nuclear Energy Plant is the largest single nuclear energy new build project in the world, with four APR-1400 units under simultaneous construction. Construction of Unit 1 commenced in 2012 and at full operational capacity, the four units will deliver up to a quarter of the UAE’s electricity needs from carbon-free nuclear energy. The project as a whole is now 79 percent complete, with Unit 1 being 95 percent complete.